What Projects is for
Projects sits on top of Halo, which stays the system of record. Projects adds what Halo has no place for: phases, task lengths, links between tasks ("this waits for that"), blocks, milestones and baselines. From those it works out a forecast (when each task and project will really finish) and a health colour for every project.
Use it to spot slipping work, re-plan dates, share out project hours and report on work done.
Live Halo
Projects reads Halo every 10 minutes: open projects and mini projects, every task under them, budgets, milestones, statuses, people, recent activity and last week's project time. Pull now reads it again straight away. The top of each page says when Halo was last read.
Changes made here go to Halo: dates, status, who it's assigned to, estimates, private notes, and new tasks from the capacity board. They go only while a hub admin has ticked Allow writes for Projects in Settings › Connections. Until then they wait on Halo sync and data, and each read from Halo keeps them on top of what Halo says, so nothing is lost.
Also live:
- Purchase orders come from PO Tracker after each read: they show on the project's Items tab with delivery status and ETA. A task whose PO hasn't arrived waits for it ("Hold tasks for hardware" rule), and the hold clears on delivery.
- Leave comes from Xero Payroll every 6 hours, once a hub admin has connected Xero in Settings › Connections. Capacity targets are set in Team settings.
- Teams messages go as a chat from the Locto Projects bot once Send to Teams is on (Automation › Teams messages), at the set times on weekdays.
Who can do what
Your access is set per tool by hub admins in Settings › People & access (see People and access). Your role shows in the top bar.
| Level | What you can do in Projects |
|---|---|
| None | No access. |
| View | Overview, Timeline, Projects and Tasks, read only. You can't change anything, including Pull now. |
| User | Overview, Timeline, Projects and Tasks. Change only tasks assigned to you: status, assignee, dates, estimate, length, blocks and notes. You can also move your own tasks on a plan and accept new dates for them. (Shown as "Project team".) |
| Admin | Every page, including Capacity, Work completed, Automation, Import a plan and Halo sync and data, and anything: links, phases, milestones, baselines, budgets, alert notes, saving the capacity board, settings and rules. (Shown as "Project manager".) |
If you give one of your tasks to someone else, you can't change it after that.
Finding your way around
The left menu shows a count of projects off track (Overview) and date changes to review (Automation).
Most pages share the same filters: person (or Me), client, health, and All / Projects / Mini projects. A mini project is a single Halo ticket with no tasks. Filters are kept in the page address, so you can share a filtered view.
The page picks up other people's changes every 20 seconds. Small ? icons explain things: hover for a tip, click for this page.
Health, slip and baselines
The baseline is the plan you measure against: either a baseline a project manager saved, or the plan as it stood on the baseline date in sync settings. Slip is how many working days the forecast finish is after the baseline finish. Working days skip weekends and SA public holidays.
Health colours
| Health | Means |
|---|---|
| Off track (red) | More than 10 working days late, over budget, or 3 or more tasks past their Halo target date. |
| At risk (amber) | More than 3 days late, over 85% of budget used with less than 70% of tasks done, no budget in Halo, no activity for 3 weeks, 1 or 2 tasks past their target, or tasks not started though their start date has passed. |
| On track (green) | None of the above. |
A project marked open-ended has no finish date, so it never shows as slipping or overdue. Budget and activity alerts still apply.
Halo statuses
Boards group Halo statuses into columns:
| Column | Halo statuses |
|---|---|
| Not started | New, Not Yet Active, Replied, Reassigned, Reopened |
| Scheduled | Scheduled |
| In progress | In Progress, Action Required, Hardware Received, Ready for Processing |
| Waiting | With User, With Supplier, Awaiting Approval, Parked |
| Done | Closed, Invoiced |
Overview
Tiles count projects by problem, people over capacity and date changes to review. Click a tile to filter or jump there. Needs attention lists each live alert. Next two weeks shows milestones, phase ends, mini projects due and leave.
Timeline
Every open project on one chart, by weeks or months. Expand a project to see its phases. This page is view only.
Projects list
Every open project with its lead, progress, budget, forecast finish, slip and health. Search by name, client or ticket number.
A single project
The top shows forecast finish, budget used, tasks done, critical tasks (open tasks with no slack: if they slip, the project slips) and tasks waiting or blocked. Project managers can Mark open-ended and Save baseline (the old baseline is kept in history).
Plan
An editable Gantt chart. Drag a bar to move a task, drag its end to change its length, or use Add days to to add working days to a task. Project managers can also link tasks and add milestones. Changes stay a draft until Save to Halo, which lists every task whose dates change, including tasks that wait for the ones you moved. Each gets a private Halo note.
Board
Tasks in status columns, filtered by phase. Drag a card to change its Halo status. Dropping on Waiting asks you to block it.
Tasks tab
Every task with assignee, status, hours, links, baseline and forecast finish, and slack.
Budget
Hours used against each Halo budget line (Remote, On-site, After hours) and their value. Imported projects also show a budget per task. Project managers can Update budget (a reason is required).
Items
Purchase orders, sales order lines and stock on the project, with delivery status from PO Tracker. Tasks waiting on hardware can't start until the day after delivery.
Health and notes
Every alert, plus changes made here and Halo notes. Project managers can Add note to an alert: say what's happening and when to check again. The alert stops counting until that date, and the note goes on the Halo project. Make live again removes the note. Anyone who can change the tasks can Push them 1 week or Start them next week.
The task panel
Click any task to open it. You can change status, assignee, Halo start and target dates, estimate and length in working days, and add a private Halo note. Project managers can also change the phase and what the task waits for.
Blocking a task
Mark blocked records who you're waiting on (client, supplier or internal), why, and when it should clear. Overdue alerts pause until then and anything waiting for the task moves out. It can also set the Halo status to With User, With Supplier or Parked. Clear puts the old status back.
Tasks
All open tasks (and tasks done in the last 30 days) across projects, as a Board, Gantt or Calendar. On the board, choose columns by Status, Person (drag to reassign) or Project.
Capacity
Planned project hours per person against their range (minimum, ideal, maximum hours a week).
- Team board: the next six weeks, person by person. Each card is one project's hours that week. Drag a card to another week or person, or use Add hours to allocate new time on a project.
- Project timeline: every project on a week grid with the team's weekly load underneath. Drag a project to slide its tasks that haven't started.
Anyone can try changes (they stay on your computer), but only a project manager can Review and save. Saving reassigns tasks, moves dates and turns new hours into Project Tasks. Team settings shows each person's weekly range; project managers can change it.
Work completed
Project time logged (Halo's Project Hours report) by person, project or client and by labour type, plus tasks closed. Only 16–22 Nov 2026 is available in this build. Download a CSV or Export PDF.
Automation
- Date changes to review: tasks past their Halo target that the forecast says will finish later. Accept sets new dates on the task and everything that waits for it. You can accept your own tasks; Accept all is for project managers.
- Teams messages: the morning messages for each person, each project lead and the project manager, plus a weekly summary. Preview what anyone would get today.
- Rules: what should happen when something changes. Project managers can turn rules on or off, add or remove them. In this build rules are recorded but don't act on their own.
Import a plan
On live Halo a plan goes onto a project that already exists in Halo: create the project there first (Claude's Halo create-project skill does it from a sales order). Open the planner file, choose the Halo project and Add the tasks in Halo. Each task becomes a Project Task under the project, created through Halo sync and data. Phases, lengths and links stay in Projects; the project's Halo budgets are left as they are.
Halo sync and data
- Live Halo: when Halo was last read, whether Projects may write to it, and every change on its way: Waiting, Sent or Refused (with Halo's reason). A project manager can Try again or Drop a change; dropping it lets the next read put back what Halo has.
- Changes made here: what each change was, newest first.
- Sync settings (project managers): webhooks, the nightly check time, whether rules may write dates, private notes on every change, and the baseline date.
- Data quality in Halo: open tasks with no dates, no assignee, past target or no estimate; support tickets filed under project tasks; projects with no budget. Click a row to see them.
Leave and public holidays
Leave comes from Xero and SA public holidays are built in. Both reduce capacity and show on the calendar. You can't enter leave in Projects.
Using Projects with Claude
Projects has no Claude tools yet.
Problems and questions
"Isn't assigned to you." You can only change your own tasks. Ask a project manager.
"You can view Projects but not change it." Your hub level is View. Ask a hub admin.
My plan changes vanished. Unsaved plan changes are discarded when you leave the project. Unsaved capacity changes stay in your browser until you save or discard them.
Dates didn't change in Halo. Check Halo sync and data: if the change is Waiting, writes are off for Projects (a hub admin ticks Allow writes in Settings › Connections); if it's Refused, Halo's reason is shown next to it.